A project can have a complete set of drawings marked Issued for Construction (IFC) and still require dozens, or hundreds, of additional drawings before fabrication and installation are complete.

That often creates confusion for project owners.

If the design has already been issued for construction, why does a structural steel fabricator still need shop drawings? Why does an equipment supplier submit another drawing showing dimensions and connections? And if the engineer reviews those shop drawings, who is ultimately responsible for the information on them?

The short answer is that IFC drawings and shop drawings serve different purposes.

IFC drawings communicate the engineering and design requirements released for construction. Shop drawings develop the detailed fabrication, assembly, equipment, or installation information needed to execute specific portions of that design.

Understanding where one ends and the other begins is important because drawing errors, unidentified deviations, outdated revisions, and unclear responsibilities can quickly turn into RFIs, fabrication changes, site rework, and schedule delays.

This guide explains the difference between IFC drawings and shop drawings, how the review process normally works, and what project owners should confirm before construction begins.

What Are IFC Drawings?

IFC drawings are drawings formally issued for construction after the applicable engineering development, coordination, checking, and approval processes have been completed.

The term IFC means Issued for Construction.

An important distinction is that IFC describes the status of a document, rather than a particular engineering discipline or drawing format.

A project may therefore have IFC:

  • Civil drawings
  • Structural drawings
  • Process drawings
  • Piping drawings
  • Mechanical drawings
  • Electrical drawings
  • Instrumentation and control drawings
  • Site plans
  • General arrangement drawings
  • Construction details

For example, a structural foundation plan may progress through several internal or client review revisions before being formally issued as an IFC drawing.

At that point, it becomes part of the controlled information being used to construct the work.

However, owners should be careful about assuming that “IFC” automatically has exactly the same contractual meaning on every project. The governing contract, specifications, document-control procedures, and project delivery model ultimately determine which documents form the construction requirements and how revisions are managed.

What Information Do IFC Drawings Typically Contain?

Depending on the discipline, IFC drawings may establish information such as:

  • Locations and elevations
  • Equipment arrangements
  • Structural member sizes
  • Foundation dimensions
  • Design loads
  • Piping routes
  • Utility alignments
  • Electrical distribution
  • Equipment connections
  • Material requirements
  • Construction details
  • Design notes
  • Interfaces between systems

The level of detail should be sufficient to communicate the engineering design, but IFC drawings do not necessarily contain every piece of information a fabricator or supplier needs to manufacture a component.

That is one reason shop drawings exist.

IFC drawings vs shop drawingsWhat Are Shop Drawings?

Shop drawings are documents prepared to show the detailed information required to fabricate, assemble, supply, or install a particular portion of the work.

Depending on the project, they may be prepared by:

  • Contractors
  • Subcontractors
  • Structural steel fabricators
  • Equipment manufacturers
  • Suppliers
  • Specialty contractors
  • Detailers
  • Specialty design professionals

Engineers and Geoscientists BC describes shop drawings broadly as drawings and related information used to illustrate details of a portion of the work, and its guidance notes that they may be prepared by fabricators, suppliers, equipment manufacturers, subcontractors, contractors, or others retained by those parties.

What Do Shop Drawings Usually Show?

Depending on the component, a shop drawing may include:

  • Exact fabrication dimensions
  • Member lengths
  • Connection geometry
  • Plates
  • Bolts
  • Welds
  • Hole locations
  • Material grades
  • Component identification
  • Equipment dimensions
  • Anchor bolt locations
  • Supports
  • Clearances
  • Assembly information
  • Installation arrangements
  • Interface dimensions

For equipment, shop or vendor drawings can also contain information such as manufacturer, model, weight, operating characteristics, electrical data, dimensions, performance information, and installation arrangements. These are among the types of information identified in the EGBC shop drawing guidance.

In practical terms, IFC documentation establishes the engineering requirements, while shop drawings take those requirements into the level of detail needed for a particular supplier, fabricator, or installer to execute its part of the work.

IFC Drawings vs. Shop Drawings: Key Differences

The simplest comparison is not that one is “better” or “more detailed” than the other. They exist for different purposes.

Factor IFC Drawings Shop Drawings
Primary purpose Communicate engineering and design requirements released for construction Develop fabrication, assembly, equipment, or installation details
Typically prepared by Engineering or design consultant Contractor, subcontractor, fabricator, supplier, manufacturer, or specialty designer
Project stage Developed through detailed design and issued before applicable construction Prepared after relevant design requirements are available and before fabrication or installation
Main focus What the designed project requires How a specific component or system will be fabricated, supplied, or installed
Typical content Layouts, sizes, loads, design details, system requirements Exact dimensions, connections, member marks, equipment data, fabrication information
Design responsibility Generally associated with the responsible design professional, subject to project scope Depends on the component and whether delegated or specialty design is involved
Review process Design checking and project approval before issue Contractor coordination followed by consultant review where required
Deviations Establishes the applicable design basis Proposed departures should be clearly identified and resolved

A Useful Way to Think About the Difference

Consider a steel platform.

The structural IFC drawings may show:

  • Platform location
  • Elevation
  • Beam and column sizes
  • Design loads
  • General framing
  • Foundation requirements
  • Connection design requirements

The steel fabricator’s shop drawings may then show:

  • Individual piece marks
  • Exact lengths
  • Plate dimensions
  • Bolt patterns
  • Weld sizes
  • Hole locations
  • Connection geometry
  • Fabrication notes
  • Erection references

Both drawing sets are necessary, but they are solving different problems.

Why Are Shop Drawings Needed If IFC Drawings Already Exist?

This is one of the most common questions owners have when they first encounter the submittal process.

Why not simply put every fabrication detail into the IFC drawings?

In most projects, that would be impractical and could blur responsibility between the design team and the parties actually manufacturing the components.

Fabricators Work With Their Own Production Requirements

Different fabricators may use different:

  • Connection preferences
  • Detailing standards
  • Equipment
  • Manufacturing processes
  • Stock sizes
  • Assembly approaches

The engineering documents establish the required performance and design constraints. The shop drawings translate those requirements into information appropriate to the selected supplier or fabricator.

Final Vendor Information May Not Exist During Detailed Design

Equipment selection sometimes continues while engineering is advancing.

The IFC package may establish:

  • Required capacity
  • Approximate dimensions
  • Design loads
  • Connections
  • Power requirements
  • Equipment location

Once a vendor is selected, the project receives the final:

  • Footprint
  • Weight
  • Anchor pattern
  • Nozzle locations
  • Connection details
  • Electrical data
  • Maintenance clearances

That information may then need to be coordinated with the engineering design.

Fabrication Requires More Detail Than General Design Documentation

A steel fabricator cannot manufacture a beam simply from a framing plan showing a member designation.

Fabrication requires exact piece information.

Similarly, an equipment supplier needs to communicate exactly what will be delivered, not just what performance was specified.

Who Is Responsible for IFC Drawings and Shop Drawings?

Responsibilities vary by contract, jurisdiction, discipline, project delivery method, and whether specialty or delegated design is involved.

Still, a typical arrangement may look broadly like this:

Activity Owner Design Engineer Contractor Fabricator / Supplier
Define project requirements ✓ Supports
Develop engineering design ✓
Issue engineering drawings for construction ✓
Coordinate construction work ✓ Supports
Prepare shop drawings Coordinates ✓
Verify field dimensions ✓ ✓
Identify proposed deviations ✓ ✓
Review shop drawings for applicable design conformance ✓
Fabrication details Responsible through contractual chain ✓
Construction means and methods ✓ As applicable

This table is only a general illustration. The contract documents should define the actual responsibility structure on a specific project.

One important principle is that consultant review of a shop drawing does not automatically transfer all responsibility for that shop drawing to the consultant.

That distinction matters.

What Does Shop Drawing Review Actually Mean?

When an engineer reviews a shop drawing, the engineer is not necessarily re-performing every task carried out by the detailer, fabricator, contractor, or supplier.

The review normally focuses on matters relevant to the engineering design responsibility.

Depending on the project and scope, this may include reviewing:

  • General conformance with the design intent
  • General arrangement
  • Applicable design criteria
  • Specified design loads
  • Materials affecting the engineering design
  • Major system interfaces
  • Connections to the primary design
  • Dimensions that materially affect the engineering work
  • Proposed departures from the design requirements

The EGBC professional practice guideline states that the registered professional of record reviews shop drawings for conformity to the design concept and general arrangement. It also notes that such review does not relieve the contractor of responsibility for errors or omissions in the shop drawings or compliance with the contract documents.

That distinction is particularly important for owners.

A consultant review should not automatically be interpreted as verification of every:

  • Field dimension
  • Quantity
  • Fabrication dimension
  • Construction sequence
  • Contractor means and methods
  • Site safety measure
  • Material take-off
  • Fabrication tolerance

Those responsibilities depend on the contract and the role of each party.

Does an Engineer “Approve” Shop Drawings?

The word approval should be used carefully.

Projects may use review statuses such as:

  • Reviewed
  • Reviewed as Noted
  • Revise and Resubmit
  • Not Acceptable
  • No Exceptions Taken

The exact wording varies between organizations and contracts.

What matters is that everyone understands the scope and meaning of the review.

For example, a review stamp indicating general conformance with the design concept is different from accepting responsibility for the fabricator’s dimensions or construction procedures.

EGBC guidance recommends wording that reflects the nature of the professional review and specifically distinguishes that review from the contractor’s continuing responsibilities.

For owners, the practical lesson is simple:

Do not rely on the word “approved” without understanding what the review actually covers.

The project specifications and submittal procedures should make this clear before shop drawings begin circulating.

What Happens When a Shop Drawing Conflicts With the IFC Drawings?

A shop drawing should not quietly rewrite the design.

Differences do occur, however.

They may arise because of:

  • Fabricator preferences
  • Final vendor information
  • Material availability
  • Field conditions
  • Constructability concerns
  • Equipment substitutions
  • Coordination conflicts
  • Changes requested by the owner

When this happens, the deviation needs to be handled deliberately.

1. Identify the Difference

The contractor, fabricator, or supplier should clearly flag the proposed deviation instead of expecting the consultant to discover it during review.

EGBC guidance states that contractors should notify the professional of record in writing of deviations from the contract document requirements when shop drawings are submitted.

2. Determine Whether It Is a Clarification or a Design Change

Some issues can be resolved without changing the design intent.

Others cannot.

If the proposed shop drawing changes a critical dimension, loading condition, material, connection, equipment requirement, or interface, engineering review may be required.

3. Review the Wider Project Impact

A small-looking change can cross several disciplines.

Moving a piece of equipment may affect:

  • Foundations
  • Structural supports
  • Piping
  • Electrical cabling
  • Instrumentation
  • Drainage
  • Access
  • Maintenance clearances

Changing one drawing without checking these interfaces can create another problem elsewhere.

4. Document the Accepted Change

If a deviation is accepted, the decision should be incorporated into the project’s controlled information in the manner required by the contract and document-control process.

Depending on the situation, that may involve:

  • RFI response
  • Site instruction
  • Supplemental detail
  • Design sketch
  • Change documentation
  • Revised IFC drawing

The key point is traceability.

Someone reviewing the project several months later should be able to understand what changed and which document now governs the work.

The Typical Shop Drawing Workflow Before Fabrication

The precise workflow varies, but a well-controlled process usually follows this sequence:

IFC / Contract Requirements

↓

Shop Drawing Prepared by Fabricator, Supplier, or Contractor

↓

Subcontractor Review and Coordination

↓

Contractor Review

↓

Submission to Consultant

↓

Engineering Review

↓

Comments or Required Revisions

↓

Resubmission if Required

↓

Authorization to Proceed

↓

Fabrication / Installation

The contractor review step matters.

Before the design consultant receives the shop drawing, the contractor should normally have coordinated it with the work, relevant field dimensions, and other project requirements.

EGBC’s guidance recommends contractor review before submission to the professional of record and states that fabrication or manufacture should not commence until the required professional review has occurred and the contractor has provided authorization to proceed.

Skipping steps to save a few days can create considerably more work if components are fabricated incorrectly.

Practical Example: Structural Steel Shop Drawings

Consider a new steel equipment platform.

The structural engineer’s IFC package establishes the primary engineering design.

The IFC Drawings May Show

  • Structural grid
  • Platform elevations
  • Column locations
  • Beam and column sizes
  • Design loads
  • Bracing
  • Foundation locations
  • General connection requirements

The steel fabricator then develops shop drawings.

The Shop Drawings May Show

  • Individual member marks
  • Exact beam lengths
  • Plate sizes
  • Connection geometry
  • Bolt sizes and locations
  • Weld requirements
  • Hole locations
  • Fabrication notes
  • Erection references

During detailing, the fabricator discovers that a proposed connection conflicts with a mechanical line running beside the platform.

There are two possible ways to handle this.

The Wrong Approach

The shop detailer changes the connection geometry, fabrication proceeds, and the modification is only noticed when the steel reaches site.

At that point, the project team may need to determine whether the altered connection still satisfies the structural design.

The Better Approach

The conflict is identified during shop drawing preparation.

The contractor flags the issue.

Structural and mechanical teams review the interface.

A technically acceptable solution is developed and documented.

The revised shop drawing is then issued through the required review process before fabrication.

That is the real purpose of drawing coordination: resolving uncertainty while changes are still relatively inexpensive to make.

Practical Example: Equipment Vendor Drawings

The same principle applies outside structural steel.

Suppose a project includes a new process pump.

During detailed design, the engineering team establishes:

  • Required flow
  • Required pressure
  • Equipment location
  • Approximate operating load
  • Piping interfaces
  • Electrical requirements
  • Preliminary foundation requirements

The pump is later purchased from a specific manufacturer.

The final vendor drawings show:

  • Actual equipment footprint
  • Operating weight
  • Anchor bolt arrangement
  • Nozzle locations
  • Motor details
  • Electrical characteristics
  • Maintenance clearances

The final pump is slightly heavier and longer than assumed during design.

That information is not relevant only to the mechanical team.

It may affect:

  • Foundation design
  • Structural loads
  • Piping geometry
  • Cable routing
  • Equipment access
  • Maintenance space

This is why vendor and shop drawing reviews can require multidisciplinary coordination rather than a simple checkmark on a submittal form.

IFC Drawings, Shop Drawings, and As-Built Drawings Are Not the Same

These terms are sometimes mixed together even though they describe different stages of project information.

Drawing Type Main Question
IFC Drawing What engineering/design has been released for construction?
Shop Drawing How will this particular component be fabricated, supplied, assembled, or installed?
As-Built / Record Documentation What was ultimately constructed or recorded after project changes?

As-built and record drawings deserve their own distinction.

For example, APEGA describes as-built drawings as documents reflecting installed, fabricated, constructed, or commissioned conditions and notes that material changes should be addressed through appropriate controlled change documentation rather than simply being left for later redline capture.

The terminology and authentication requirements can also vary by jurisdiction and project, so owners should define their closeout requirements early.

Where IFC and Shop Drawings Fit in the Project Lifecycle

The drawing process becomes easier to understand when viewed as part of the overall engineering lifecycle.

FEED

↓

Detailed Design

↓

Issued-for-Construction Documentation

↓

Shop Drawings and Technical Submittals

↓

Procurement and Fabrication

↓

Construction

↓

Field Changes and Construction Support

↓

Project Records / Closeout Documentation

During FEED, major systems and design criteria are established.

During Detailed Design, calculations, layouts, specifications, and coordinated drawings are developed.

The IFC issue releases the relevant engineering documents for construction use.

The shop drawing and submittal process then develops supplier- and fabrication-specific information.

During construction, additional technical questions may be addressed through RFIs, revised documentation, field reviews, or other construction-support processes.

The important point is that the stages are connected.

Poor information control at one stage usually appears as additional work in the next.

Common Drawing Problems Project Owners Should Watch For

Project owners do not need to personally review every weld or bolt on a shop drawing.

They should, however, make sure the project has a reliable process for controlling information.

Shop Drawings Are Submitted Too Late

Shop drawings often sit directly on the procurement and fabrication path.

If they arrive late, the engineering team may face pressure to shorten review time to protect the schedule.

That leaves less time to resolve real technical issues.

A submittal register tied to procurement and construction milestones helps expose these risks earlier.

Fabrication Starts Before Required Reviews Are Complete

Starting fabrication early may appear to save time.

If significant comments emerge afterwards, however, the project may face:

  • Refabrication
  • Material waste
  • Additional cost
  • Schedule disruption

The shop drawing workflow should therefore identify clearly when fabrication is permitted to proceed.

Deviations Are Hidden Inside the Drawings

A reviewer should not have to compare every line of a shop drawing with every IFC document to discover that a supplier has changed the design.

Proposed departures should be clearly identified.

The Contractor Has Not Coordinated the Submittal

Consultant review should not be the first time anyone notices that a shop drawing conflicts with another trade.

Contractor coordination is an essential step before submission.

An Outdated IFC Revision Is Used

A perfectly detailed shop drawing can still be wrong if it was prepared from superseded engineering information.

The shop drawing should reference the relevant design drawing and revision.

EGBC guidance specifically calls for shop drawings to identify applicable design drawing and revision information.

Shop Drawing Review Is Treated as a Transfer of Design Responsibility

Consultant review does not automatically make the consultant responsible for everything shown on a contractor or supplier drawing.

Roles should remain consistent with the contract and applicable professional obligations.

Technical Decisions Are Made Through Informal Messages

A phone call can resolve an immediate conversation, but it may not provide the controlled record needed by the rest of the project team.

Material changes should move through an appropriate documented process.

IFC drawings vs shop drawingsWhat Should Project Owners Verify Before Construction Starts?

Owners do not need to manage every technical detail themselves, but they should confirm that the process around those details has been defined.

Before fabrication and construction accelerate, ask:

  • Is the current IFC drawing set clearly identified?
  • Is there a controlled drawing register?
  • How are superseded revisions removed from use?
  • Which components require shop drawings?
  • Who is responsible for preparing each submittal?
  • Who performs the contractor’s coordination review?
  • Which submittals require professional engineering involvement?
  • How must proposed deviations be identified?
  • What information must accompany a shop drawing?
  • What are the planned review turnaround times?
  • How are urgent submittals handled?
  • Who can authorize fabrication?
  • How are consultant comments tracked and closed?
  • How are accepted design changes incorporated into project documents?
  • Who maintains the final project record?

These questions may appear administrative, but each one can have a direct effect on engineering coordination, procurement, construction, and schedule.

How Drawing Coordination Affects Cost and Schedule

Problems with IFC and shop drawings rarely remain confined to the drawing register.

A poorly coordinated submittal can lead to:

  • Additional RFIs
  • Refabrication
  • Site rework
  • Delayed procurement
  • Material waste
  • Field modifications
  • Change orders
  • Installation conflicts
  • Construction delays

The earlier an inconsistency is identified, the more options the project team usually has for resolving it.

Consider a steel connection conflict.

Finding it while a shop drawing is still on-screen may require a design discussion and drawing revision.

Finding the same conflict after steel has been fabricated, coated, shipped, and erected creates a much different problem.

The value of drawing control is not producing more documents. It is reducing uncertainty before material is purchased, fabricated, or installed.

What Is the Project Owner’s Role?

The owner should not become the shop drawing detailer or substitute for the design consultant.

The owner’s role is primarily to make sure the project has appropriate governance around the process.

That means confirming that responsibilities are defined for:

  • Engineering
  • Contractor coordination
  • Fabrication
  • Submittal preparation
  • Technical review
  • Schedule management
  • Change management
  • Document control

Owners should also make sure the contract documents address practical questions such as:

  • Required submittals
  • Review periods
  • Resubmission requirements
  • Fabrication authorization
  • Treatment of deviations
  • Delegated design
  • Document retention
  • Final record requirements

Where complex projects involve civil, structural, process, mechanical, and electrical systems, the owner should also ensure that changes are not being considered in isolation.

A drawing process is only as effective as the coordination behind it.

Key Takeaways for Project Owners

  • IFC means Issued for Construction and generally describes the status of engineering or design documentation released for construction use.
  • Shop drawings provide project-specific fabrication, equipment, assembly, or installation information.
  • IFC and shop drawings serve different purposes; one does not simply replace the other.
  • Contractors, suppliers, fabricators, and consultants can have different responsibilities within the shop drawing process.
  • Shop drawing review does not automatically transfer contractor or fabricator responsibilities to the engineer.
  • Proposed departures from the engineering requirements should be clearly identified.
  • Material changes need a controlled technical review and documentation process.
  • Contractors should coordinate shop drawings before submitting them for consultant review.
  • Fabrication should follow the project’s defined submittal and authorization process.
  • Revision control is just as important as the quality of the drawings themselves.

Conclusion

For project owners, the most useful way to think about IFC drawings vs. shop drawings is not as competing sets of documents.

They are connected stages in the same information chain:

Engineering Design → IFC Documentation → Shop Drawings → Review → Fabrication → Construction

IFC drawings establish the relevant engineering basis released for construction. Shop drawings take portions of that design into the fabrication, supplier, or installation detail required for execution.

Problems arise when the connection between those stages breaks down.

An unidentified deviation, an outdated IFC revision, an uncoordinated submittal, or an informal design change can eventually appear in the field as rework or delay.

For owners, the goal is therefore not to eliminate shop drawings or to push every detail into the IFC package. It is to establish a clear process in which responsibilities, revisions, deviations, reviews, and design changes can be followed from engineering through construction.

Frequently Asked Questions

What does IFC mean on engineering drawings?

IFC means Issued for Construction. It indicates that a drawing has been formally issued for use in construction according to the project’s document-control and approval process.

The exact contractual significance of an IFC designation should still be interpreted together with the contract documents and project procedures.

What is the difference between IFC drawings and shop drawings?

IFC drawings communicate the applicable engineering and design requirements released for construction. Shop drawings provide more specific information about how particular components, equipment, assemblies, or systems will be fabricated, supplied, or installed.

They are related documents, but they serve different purposes.

Who prepares shop drawings?

Shop drawings may be prepared by contractors, subcontractors, fabricators, equipment manufacturers, suppliers, detailers, or specialty professionals, depending on the type of work.

The contractor typically coordinates the submittal process before the drawings are forwarded for consultant review.

Who reviews shop drawings?

Shop drawings commonly go through contractor review and coordination before being submitted to the appropriate design consultant or professional of record.

The consultant’s scope of review depends on the project requirements, discipline, contract, and professional responsibilities.

Can construction or fabrication start before shop drawings are reviewed?

Where shop drawing review is required by the project documents, fabrication should follow the defined review and authorization procedure.

EGBC guidance states that manufacture or fabrication should not begin until the professional of record has completed the required review, returned the documents to the contractor, and the contractor has authorized the work to proceed.

Can a shop drawing change the IFC design?

A shop drawing may propose a departure from the IFC or contract requirements, but the departure should be clearly identified and reviewed through the project’s technical and change-control process.

A shop drawing should not be used to introduce an undocumented design change.

Does shop drawing review make the engineer responsible for all information on the drawing?

Not necessarily.

The scope of consultant review is normally limited to matters relevant to the consultant’s professional responsibility and the requirements established in the contract.

For example, EGBC guidance distinguishes consultant review for general conformance with the design concept from the contractor’s continuing responsibility for shop drawing errors, omissions, and compliance with the contract documents.

What happens if a shop drawing conflicts with an IFC drawing?

The conflict should be identified and resolved before the affected work proceeds.

Depending on the issue, resolution may involve coordination, an RFI, engineering review, revised shop drawings, a supplemental detail, or formal revision to the engineering documentation.

Are shop drawings considered construction drawings?

They are both used within the construction process, but the terms should not be treated as interchangeable.

IFC construction drawings are typically issued by the design team to communicate the engineering design. Shop drawings are generally prepared by parties involved in fabrication, supply, or installation to develop particular portions of that design in greater execution detail.

What is the difference between IFC, shop drawings, and as-built drawings?

IFC drawings show the engineering/design information released for construction.

Shop drawings show fabrication, equipment, assembly, or installation information for specific parts of the work.

As-built or record documentation reflects information about what was ultimately installed or constructed, subject to the project’s specific definitions and documentation requirements.