Our FEED engineering services bring together technical requirements, design criteria, site conditions, engineering interfaces, equipment needs, cost inputs, scheduling considerations, procurement requirements, and project risks before the project advances into detailed design and construction.
By developing the project scope at the right level of detail, FEED helps owners make better-informed investment decisions, reduce uncertainty, and establish a more reliable foundation for the next stage of project development.
Axispoint provides engineering feasibility study services for mining, infrastructure, energy, industrial, and commercial projects across Canada.

Engineering Consulting

Discuss Your FEED Requirements

What Is Front-End Engineering Design?

Front-End Engineering Design, commonly referred to as FEED, is the project development stage between feasibility or concept selection and detailed engineering.

A feasibility study helps determine whether a project should proceed and which development option is preferred. FEED takes that selected option and develops it into a more clearly defined technical and execution basis.

During FEED, the project team establishes and coordinates the information required to answer questions such as:

  • What systems and facilities are included in the project?
  • What are the project’s design criteria and operating requirements?
  • Which technical assumptions still require confirmation?
  • What equipment and infrastructure will be required?
  • How will the engineering disciplines interact?
  • What site conditions or existing facilities affect the design?
  • Which approvals, investigations, and vendor inputs are required?
  • What are the major technical and execution risks?
  • What information is needed to support cost and schedule development?
  • Is the project sufficiently defined to proceed into detailed design?

A FEED package is more developed than a conceptual or feasibility-level design, but it is not normally a construction-ready detailed design package.

Its purpose is to define the project well enough that the owner, engineering team, procurement group, and project stakeholders can move forward using a shared technical basis.

For certain Canadian clean-energy project programs, Natural Resources Canada similarly distinguishes FEED-stage documentation from complete detailed engineering documentation issued for construction.

Feasibility Studies → FEED → Detailed Design → Construction Support

When Does a Project Need FEED?

FEED is most valuable when a project has progressed beyond initial feasibility but still contains significant technical, cost, schedule, procurement, or execution uncertainty.

Before a Major Capital Commitment

Before committing substantial capital, project owners need more than a high-level concept.

FEED helps establish what the project includes, what information supports the design, what major risks remain, and what conditions must be resolved before execution.

This creates a stronger technical basis for project authorization, funding decisions, and internal approvals.

Before Detailed Engineering Begins

Detailed design becomes inefficient when the project basis is still changing.

If fundamental decisions about capacity, layout, equipment, site development, utilities, interfaces, or operating requirements remain unresolved, the detailed engineering team may repeatedly redesign completed work.

FEED helps resolve major project decisions before the project enters the more resource-intensive detailed design stage.

When the Project Scope Is Not Clearly Defined

A project may have a clear business objective but an incomplete technical scope.

For example, an owner may know that a facility must increase capacity, replace aging equipment, improve reliability, or expand into a new site. However, the required systems, interfaces, modifications, supporting infrastructure, and construction constraints may not yet be understood.

FEED converts the project objective into a defined engineering scope.

When Multiple Technical Options Remain

Some projects enter FEED with several possible layouts, equipment arrangements, utility strategies, or implementation approaches.

Targeted option evaluation during FEED can help confirm which approach should become the basis for detailed design.

The comparison may consider:

  • Technical performance
  • Capital implications
  • Operating requirements
  • Constructability
  • Maintainability
  • Site constraints
  • Utility demand
  • Equipment availability
  • Project schedule
  • Future expansion
  • Interfaces with existing facilities

Before Procuring Long-Lead Equipment

Long-lead equipment can influence the project schedule, facility layout, structural requirements, electrical demand, piping configuration, access needs, and construction sequence.

FEED can establish preliminary equipment requirements, identify long-lead items, and define the vendor information needed before the surrounding design is finalized.

When Cost and Schedule Estimates Need Better Definition

Cost estimates and project schedules are only as reliable as the technical scope behind them.

FEED develops the equipment information, layouts, quantities, system requirements, procurement assumptions, construction considerations, and engineering inputs required to improve the basis of the estimate and schedule.

The level of estimate accuracy depends on the project, available information, required FEED maturity, and estimating methodology.

For Brownfield Modifications and Facility Expansions

Modifications within operating facilities often contain significant uncertainty.

Existing records may be incomplete. Equipment must remain operational. Tie-ins may require shutdowns. New systems must fit within constrained spaces, and one modification may affect several engineering disciplines.

FEED provides a structured stage for verifying existing conditions, identifying interfaces, evaluating tie-in requirements, and developing an execution strategy before detailed design begins.

What Does FEED Help Project Owners Achieve?

A well-structured FEED study is intended to improve project definition, not simply increase the number of drawings produced.

Define the Technical Scope

FEED clarifies which systems, facilities, equipment, interfaces, and supporting infrastructure are included in the project.

It also identifies scope boundaries, exclusions, battery limits, owner requirements, and responsibilities between project participants.

Establish a Reliable Basis of Design

A controlled Basis of Design helps ensure that all engineering disciplines work from consistent information.

It may document:

  • Project objectives
  • Capacity and performance requirements
  • Operating conditions
  • Design life
  • Environmental conditions
  • Applicable codes and standards
  • Site information
  • Owner requirements
  • Equipment assumptions
  • Material requirements
  • Utility conditions
  • Safety and reliability criteria
  • Future expansion requirements

Improve Cost Estimate Inputs

FEED develops the technical information required to support a more informed project cost estimate.

Depending on the project, this may include:

  • Major equipment requirements
  • Preliminary quantities
  • Site development requirements
  • Utility demands
  • Structural concepts
  • Preliminary material selections
  • Procurement assumptions
  • Construction access requirements
  • Brownfield tie-ins
  • Execution constraints

FEED does not eliminate all cost uncertainty, but it helps make the basis of the estimate more visible and defensible.

Develop a More Realistic Project Schedule

The FEED process can identify activities that may influence the project schedule, including:

  • Required site investigations
  • Regulatory submissions
  • Owner decision dates
  • Vendor information
  • Long-lead equipment
  • Procurement packages
  • Detailed design dependencies
  • Seasonal construction constraints
  • Shutdowns and tie-ins
  • Construction sequencing
  • Commissioning requirements

Identify Technical Risks Earlier

Risks are less expensive to address while the project still has design flexibility.

FEED can identify risks associated with:

  • Incomplete information
  • Existing site conditions
  • Equipment selection
  • Utility capacity
  • Discipline interfaces
  • Constructability
  • Regulatory requirements
  • Operations continuity
  • Procurement
  • Material availability
  • Construction access
  • Project schedule

Support Procurement Planning

FEED can help identify the equipment, materials, services, and technical packages that may require early procurement attention.

It can also define the vendor information required to support detailed design and identify which procurement decisions must occur before certain engineering activities can be completed.

Prepare the Project for Detailed Design

A key objective of FEED is to provide the detailed engineering team with a clear and coordinated starting point.

The FEED package should identify:

  • The approved project basis
  • Confirmed design criteria
  • Major systems and equipment
  • Discipline interfaces
  • Required investigations
  • Outstanding decisions
  • Information gaps
  • Procurement dependencies
  • Project risks
  • The expected detailed design scope

Multi-Discipline Engineering 2

Our Front-End Engineering Design Scope

Axispoint develops FEED scopes based on the project’s objectives, sector, complexity, available information, required disciplines, and the decisions the FEED package must support.

Not every project requires every activity or deliverable listed below. The FEED scope should be tailored to the project rather than built around a generic checklist.

Project Definition and Basis of Design

We begin by confirming the technical and project-development basis.

This may include:

  • Project objectives
  • Owner and stakeholder requirements
  • Capacity and performance requirements
  • Operating philosophy
  • Design conditions
  • Applicable codes and standards
  • Project boundaries and battery limits
  • Scope inclusions and exclusions
  • Design assumptions
  • Required design life
  • Safety and reliability expectations
  • Future expansion considerations
  • Document and data requirements

The Basis of Design becomes a shared reference for civil, structural, process, mechanical, and electrical engineering development.

Existing Information and Site Assessment

The quality of FEED depends on the quality of the information supporting it.

Axispoint reviews available project information to determine what can be used, what requires verification, and what is still missing.

Depending on the project, the review may include:

  • Existing drawings and records
  • Site survey information
  • Geotechnical data
  • Environmental information
  • Utility records
  • Equipment data
  • Previous engineering studies
  • Operating data
  • Inspection and condition assessment reports
  • Existing facility constraints
  • Previous modifications
  • Regulatory and approval information

Data gaps are documented so that required investigations and decisions can be incorporated into the project plan.

Technical Option Development and Evaluation

Where major technical choices remain, Axispoint can develop and evaluate practical alternatives.

Potential areas of evaluation include:

  • Facility layouts
  • Equipment configurations
  • Process arrangements
  • Utility strategies
  • Site access
  • Road alignments
  • Drainage concepts
  • Structural systems
  • Tie-in locations
  • Construction sequencing
  • Expansion strategies
  • Brownfield integration approaches

Options are assessed against project-specific criteria rather than technical performance alone.

Constructability, operability, maintainability, cost awareness, schedule, risk, site conditions, and long-term project requirements may all influence the preferred solution.

Process and System Development

Process engineering helps define how the proposed system or facility must function.

Depending on the project, FEED activities may include:

  • Confirming process requirements
  • Establishing operating and design conditions
  • Developing process descriptions
  • Preparing flow diagrams
  • Establishing material or energy balances
  • Developing preliminary piping and instrumentation diagrams
  • Identifying utility requirements
  • Defining equipment duties
  • Establishing control requirements
  • Identifying process interfaces
  • Reviewing system safety and operability considerations

Equipment Definition

Major equipment decisions can affect nearly every part of the project.

During FEED, Axispoint may support:

  • Preliminary equipment selection
  • Equipment sizing inputs
  • Equipment lists
  • Preliminary data sheets
  • Duty and performance requirements
  • Material requirements
  • Space and access requirements
  • Maintenance clearances
  • Equipment loads
  • Utility connections
  • Vendor information requirements
  • Long-lead item identification

Site, Civil, and Infrastructure Development

Civil engineering during FEED establishes how the project will interact with the site.

The scope may include:

  • Preliminary site planning
  • Grading concepts
  • Drainage strategy
  • Stormwater requirements
  • Earthworks considerations
  • Road and access planning
  • Utility routing
  • Water and wastewater requirements
  • Erosion and sediment control concepts
  • Site servicing
  • Construction access
  • Interface with existing infrastructure

Structural Development

Structural FEED activities establish the preliminary basis for foundations and load-bearing systems.

This may include:

  • Structural design criteria
  • Equipment and building loads
  • Preliminary foundation concepts
  • Structural framing concepts
  • Equipment support requirements
  • Retaining structures
  • Pipe and cable support concepts
  • Existing structure modifications
  • Preliminary material selection
  • Constructability considerations

Mechanical and Piping Development

Mechanical engineering during FEED may address:

  • Major equipment requirements
  • Piping systems
  • Utility systems
  • Equipment arrangements
  • Preliminary routing
  • Tie-ins
  • Material selection
  • Mechanical design conditions
  • Access and maintenance requirements
  • Equipment handling
  • Existing system interfaces
  • Preliminary line and equipment information

Electrical, Instrumentation, and Controls Development

Electrical and controls considerations may include:

  • Preliminary electrical loads
  • Power distribution concepts
  • Single-line diagrams
  • Equipment power requirements
  • Utility supply requirements
  • Preliminary cable routing
  • Control philosophy
  • Instrumentation requirements
  • Control system architecture
  • Equipment interfaces
  • Communications requirements
  • Existing electrical system capacity

Constructability and Execution Planning

A technically sound design must also be practical to execute.

FEED may consider:

  • Construction access
  • Equipment delivery
  • Crane and lifting requirements
  • Site logistics
  • Temporary works
  • Installation sequence
  • Existing operations
  • Shutdown requirements
  • Tie-in planning
  • Weather and seasonal conditions
  • Material availability
  • Contractor interfaces
  • Construction packaging

Cost, Schedule, and Procurement Inputs

Axispoint develops and coordinates technical information that can support project controls and procurement activities.

This may include:

  • Equipment information
  • Preliminary quantities
  • Engineering work breakdown
  • Procurement package identification
  • Long-lead item identification
  • Vendor data requirements
  • Cost estimate basis inputs
  • Schedule activities and dependencies
  • Required investigations
  • Detailed design assumptions
  • Execution constraints
  • Project risk inputs

Typical FEED Deliverables

The exact deliverables depend on the project, sector, owner requirements, and the required level of definition.

A FEED package may include the following.

Project Definition Documents

  • Basis of Design
  • Design criteria
  • Project scope definition
  • Owner requirements
  • Applicable codes and standards list
  • Assumptions and constraints register
  • Battery limits
  • Interface register
  • Design responsibility matrix
  • Data gap register
  • Open-items list

Process and System Documents

  • Block flow diagrams
  • Process flow diagrams
  • Utility flow diagrams
  • Preliminary piping and instrumentation diagrams
  • Process descriptions
  • Material and energy balances
  • Equipment duties
  • Utility summaries
  • Control philosophy
  • System narratives

Equipment and Facility Documents

  • Major equipment list
  • Preliminary equipment data sheets
  • General arrangement drawings
  • Preliminary facility layouts
  • Plot plans
  • Equipment arrangements
  • Access and maintenance studies
  • Preliminary utility plans
  • Vendor information requirements

Civil and Structural Documents

  • Preliminary site plan
  • Grading and drainage concepts
  • Road and access concepts
  • Utility routing concepts
  • Earthworks considerations
  • Preliminary foundation concepts
  • Structural design criteria
  • Structural framing concepts
  • Preliminary loading information
  • Existing structure modification concepts

Mechanical, Electrical, and Controls Documents

  • Preliminary piping layouts
  • Mechanical system descriptions
  • Preliminary line information
  • Electrical load list
  • Preliminary single-line diagrams
  • Electrical distribution philosophy
  • Instrumentation requirements
  • Control system philosophy
  • Preliminary equipment interface requirements

Project Execution Documents

  • Constructability review findings
  • Project risk register
  • Procurement strategy inputs
  • Long-lead equipment list
  • Cost estimate basis inputs
  • Project schedule inputs
  • Required investigation list
  • Execution assumptions
  • Detailed design scope recommendations
  • FEED closeout and handover documentation

Our FEED Delivery Approach

1. Understand the Project

We begin by understanding the project objective, business drivers, current stage of development, available information, technical concerns, stakeholders, and decisions the FEED package must support.

The first step is not producing drawings. It is confirming what the owner needs to know at the end of FEED.

2. Confirm the Project Basis

We review existing studies, records, site information, design assumptions, operating requirements, codes, standards, and owner requirements.

Information gaps and unresolved assumptions are identified early so they can be verified, investigated, or managed.

3. Develop the Engineering Scope

The selected project concept is developed across the required engineering disciplines.

Systems, equipment, layouts, site requirements, discipline interfaces, utility needs, and operating conditions are progressively defined.

4. Coordinate the Disciplines

Civil, structural, process, mechanical, and electrical engineering decisions are coordinated around a shared project basis.

Changes in one discipline are reviewed for their effects on the rest of the project.

This multi-discipline engineering approach helps identify interface issues before they become detailed design or construction problems.

5. Review Constructability, Cost, Schedule, and Risk

Technical development is reviewed alongside execution considerations.

The project team evaluates major construction constraints, procurement dependencies, long-lead items, schedule drivers, open decisions, data gaps, and technical risks.

6. Review the FEED Package

The developing FEED package is checked and reviewed for:

  • Alignment with the Basis of Design
  • Technical consistency
  • Discipline coordination
  • Completeness
  • Constructability
  • Open issues
  • Project risks
  • Suitability for its intended purpose

Owner comments and key decisions are documented and incorporated where applicable.

7. Deliver a Controlled Project Basis

The final FEED package provides a coordinated record of:

  • The selected technical basis
  • Design requirements
  • Project scope
  • Engineering development
  • Major equipment and systems
  • Interfaces
  • Assumptions
  • Risks
  • Outstanding information
  • Recommendations for the next stage

Front-End Engineering Design (FEED)

A Multi-Discipline Approach to FEED

FEED decisions are rarely limited to one engineering discipline.

A change in equipment capacity may affect structural loads, electrical demand, piping sizes, utility requirements, facility layout, access, and site infrastructure.

A change in site elevation may affect drainage, foundations, road grades, underground utilities, and equipment connections.

Axispoint coordinates civil, structural, process, mechanical, and electrical engineering around a common project basis.

Civil Engineering During FEED

Civil engineering helps establish how the project fits within its site.

Key considerations may include grading, drainage, earthworks, roads, access, utilities, water systems, stormwater management, and construction logistics.

Structural Engineering During FEED

Structural engineering establishes preliminary foundation and structural concepts based on equipment loads, site conditions, facility requirements, durability, and project interfaces.

Process Engineering During FEED

Process engineering defines system requirements, design conditions, flow relationships, equipment duties, operating philosophy, utility requirements, and process interfaces.

Mechanical Engineering During FEED

Mechanical engineering supports equipment selection, piping, utility systems, layouts, access, maintainability, materials, tie-ins, and integration with existing facilities.

Electrical Engineering During FEED

Electrical engineering establishes preliminary loads, power distribution requirements, equipment interfaces, controls, system capacity, and electrical infrastructure needs.

FEED Services for Energy, Infrastructure, and Mining Projects

Axispoint applies its FEED approach across complex projects in the energy, infrastructure, and mining sectors.

The required scope, disciplines, deliverables, and project-development priorities vary by sector.

Energy FEED Services

Energy projects may involve brownfield modifications, equipment replacements, plant upgrades, debottlenecking, power systems, renewable energy, industrial facilities, and new developments.

FEED considerations may include:

  • Operating continuity
  • Process requirements
  • Equipment integration
  • Tie-ins and shutdowns
  • Existing utility capacity
  • Safety and reliability
  • Electrical loads
  • Control system interfaces
  • Long-lead equipment
  • Brownfield constructability

Infrastructure FEED Services

Infrastructure projects require coordination between site systems, utilities, structures, approvals, stakeholders, and long-term performance requirements.

FEED considerations may include:

  • Site development
  • Roads and access
  • Grading and drainage
  • Water and wastewater systems
  • Stormwater management
  • Utility corridors
  • Structural systems
  • Existing infrastructure
  • Municipal requirements
  • Construction staging

Mining FEED Services

Mining projects often involve demanding site conditions, remote logistics, large-scale earthworks, water management, heavy civil infrastructure, processing facilities, and operational constraints.

FEED considerations may include:

  • Mine site infrastructure
  • Haul roads
  • Water management
  • Dewatering
  • Drainage
  • Utilities
  • Processing facilities
  • Equipment foundations
  • Remote construction logistics
  • Expandability and operational continuity

FEED vs. Feasibility Study vs. Detailed Design

Although these stages are connected, they support different decisions.

Project Stage Primary Question Typical Level of Definition Typical Outcome
Feasibility Study Should the project proceed, and which option is preferred? Conceptual or preliminary Recommended development option and decision basis
FEED How should the selected project be defined and prepared for execution? Intermediate and coordinated Defined scope, systems, interfaces, cost and schedule basis
Detailed Design How will the project be procured, fabricated, and constructed? Detailed and execution-ready Final calculations, specifications, and construction documents

Feasibility Study

Feasibility focuses on technical viability, option comparison, major constraints, preliminary cost considerations, risk, and the conditions under which the project should proceed.

FEED

FEED develops the preferred concept, establishes the Basis of Design, coordinates the disciplines, defines major systems and equipment, and improves the basis for execution planning.

Detailed Design

Detailed design converts the approved project basis into final calculations, drawings, specifications, schedules, data sheets, and documentation for procurement and construction.

FEED for Brownfield and Greenfield Projects

Brownfield FEED

Brownfield projects involve modifications within or adjacent to existing facilities and infrastructure.

Key challenges may include:

  • Incomplete record drawings
  • Hidden conditions
  • Existing system capacity
  • Operational continuity
  • Limited space
  • Existing equipment interfaces
  • Tie-ins
  • Shutdown windows
  • Temporary works
  • Construction access
  • Integration with legacy systems

Brownfield FEED places particular importance on field verification, interface management, operating requirements, and practical construction sequencing.

Greenfield FEED

Greenfield projects begin without the same level of existing facility constraint, but require broader site and infrastructure definition.

Key considerations may include:

  • Site development
  • Plot planning
  • Roads and access
  • Utilities
  • Drainage
  • Facility arrangement
  • Environmental constraints
  • Construction logistics
  • Expandability
  • Future operations
  • Connection to external infrastructure

FEED Considerations for Canadian Projects

Canadian projects may involve location-specific technical, regulatory, environmental, and execution requirements.

Depending on the project, FEED may need to consider:

  • Provincial and municipal requirements
  • Applicable Canadian codes and standards
  • Professional engineering requirements
  • Cold-weather design
  • Freeze-thaw exposure
  • Snow and ice conditions
  • Drainage and spring snowmelt
  • Seasonal construction limitations
  • Remote and northern logistics
  • Material and equipment availability
  • Environmental and permitting requirements
  • Existing brownfield facilities
  • Indigenous and stakeholder considerations
  • Long-term asset durability
  • Future climate conditions

These requirements should be identified early and incorporated into the project basis rather than treated as late-stage design checks.

What Information Is Needed to Begin FEED?

The information required depends on the project, but useful starting inputs may include:

  • Project objectives
  • Feasibility or concept studies
  • Owner requirements
  • Process and operating information
  • Capacity targets
  • Existing drawings
  • Site surveys
  • Geotechnical information
  • Utility information
  • Equipment data
  • Facility records
  • Environmental information
  • Regulatory requirements
  • Cost objectives
  • Target schedule
  • Required decision dates
  • Known project risks
  • Planned procurement strategy
  • Existing facility shutdown constraints

A project does not need to have every item complete before FEED begins.

One of the first FEED activities is identifying missing information, determining which gaps materially affect the project, and developing a plan to resolve or manage them.

Why Work With Axispoint for FEED?

Integrated Multi-Discipline Engineering

Axispoint brings civil, structural, process, mechanical, and electrical engineering considerations together within one coordinated project framework.

This helps maintain consistency between systems and improves visibility at project interfaces.

Practical, Execution-Focused Engineering

Our FEED approach considers how the project will be designed, procured, constructed, operated, maintained, and integrated with its site or existing facility.

The objective is not simply to develop a technically acceptable concept, but to establish a project basis that can move forward.

Experience Across Energy, Infrastructure, and Mining

Axispoint focuses on sectors where site conditions, equipment, infrastructure, operations, constructability, and multidisciplinary coordination strongly influence project success.

Clear Assumptions and Open Items

A reliable FEED package should make uncertainty visible.

Axispoint documents key assumptions, constraints, data gaps, interfaces, risks, and outstanding decisions so that project stakeholders understand the basis of the work.

Continuity Across the Project Lifecycle

Axispoint can support projects from feasibility and FEED through detailed design, construction support, and project management.

Continuity between stages helps preserve project knowledge, design assumptions, technical decisions, and interface information as the project develops.

Canadian Engineering Support

As a Canadian multi-discipline engineering firm, Axispoint develops project solutions with consideration for applicable jurisdictional requirements, site conditions, climate, construction constraints, and owner priorities.

Build a Stronger Technical Basis for Your Project

FEED is where an approved project concept becomes a defined and coordinated basis for execution.

A well-structured FEED package helps owners understand what the project includes, what information supports it, what risks remain, and what must happen before detailed design and construction.

Axispoint supports energy, infrastructure, and mining clients with practical Front-End Engineering Design services focused on scope clarity, multidisciplinary coordination, constructability, and informed project decisions.

Frequently Asked Questions

What is Front-End Engineering Design?

Front-End Engineering Design is the stage between feasibility or concept selection and detailed design.

It develops the preferred concept into a coordinated project basis by defining design criteria, scope, systems, major equipment, interfaces, site requirements, risks, cost inputs, schedule considerations, and execution needs.

What is included in a FEED study?

A FEED study may include a Basis of Design, design criteria, preliminary calculations, layouts, equipment lists, process diagrams, preliminary P&IDs, civil and structural concepts, electrical loads, control philosophy, cost estimate inputs, schedule inputs, constructability review, and a project risk register.

The exact scope depends on the project and the level of definition required.

What is the difference between feasibility and FEED?

Feasibility determines whether a project should proceed and which option is preferred.

FEED develops the selected option into a more clearly defined technical scope and execution basis.

Feasibility asks, “Should this project proceed?”

FEED asks, “How should the selected project be defined and prepared for the next stage?”

What is the difference between FEED and detailed design?

FEED establishes the project basis, major systems, equipment requirements, layouts, scope, interfaces, and execution inputs.

Detailed design develops that basis into final calculations, drawings, specifications, schedules, and documentation suitable for procurement and construction.

Is a FEED package ready for construction?

A FEED package is not normally intended to serve as a complete construction package.

Some FEED documents may support early procurement or project planning, but construction generally requires completed detailed engineering and controlled Issued-for-Construction documentation.

When should FEED begin?

FEED should typically begin after a preferred project concept has been selected and the owner requires greater technical definition before detailed design, procurement, or major capital commitment.

A preliminary project review can determine whether the available information is sufficient to begin FEED.

How long does a FEED study take?

The duration depends on project complexity, available information, required disciplines, number of alternatives, site investigation needs, owner review periods, vendor inputs, and the required maturity of the FEED package.

A project-specific scope and schedule should be established before work begins.

What information is required to start FEED?

Useful inputs include feasibility studies, project objectives, owner requirements, site information, existing drawings, operating data, capacity requirements, equipment information, schedule targets, cost objectives, and known project constraints.

Incomplete information does not always prevent FEED from starting, but data gaps should be identified and managed.

Does FEED include a project cost estimate?

FEED can provide the technical basis and project definition required to support a more developed cost estimate.

The estimating scope, methodology, classification, accuracy range, exclusions, and responsibilities should be clearly defined for each project.

Can FEED be completed for an existing facility?

Yes. FEED is particularly valuable for brownfield modifications, expansions, equipment replacements, system upgrades, debottlenecking projects, and tie-ins within operating facilities.

These projects often require field verification, interface management, shutdown planning, and coordination with existing systems.

Which engineering disciplines are involved in FEED?

The required disciplines depend on the project.

AxisPoint’s FEED work may involve civil, structural, process, mechanical, and electrical engineering, supported by project management and other specialized technical input where required.

Can Axispoint continue into detailed design and construction support?

Yes. Axispoint supports projects across the engineering lifecycle, including feasibility studies, FEED, detailed design, construction support, and project management.

Continuing with the same engineering team can help maintain continuity between the FEED basis and subsequent project stages.